Tuesday, 6 October 2009

Update

It's been a while... Been so extremely busy, but here's the current status:

- All windows are in apart from the large window wall in living room. That is going in next week after they have removed the lift used to put the ceiling plaster boards in place.
- All ceilings downstairs now have plasterboard
- The electricians have made progress, more is needed, will come shortly!
- Inside walls have gone up!
- Matt's friend Paul has started with the skimming of the walls (spackling)
- Danne will come and help us with the painting, bless him!
- Matt and myself to start putting underfloor heating down at weekend.
- Floorboards for upstairs will be ordered
- We've found really nice wash basins for the bathrooms which we'll order
- Matt's looking into marble work top for kitchen
- I am ordering toilets (yep that also has to be done)
- we'll be ordering the new kick-ass heating pump from Nibe, called Nibe Split
- we won't be in by end of october, but HAVE to be in by the weekend after... fingers crossed everybody!



1 comment:

  1. Haven't looked at the blog for a long time so it was fun to catch up on your amazing progress. Looks really nice!

    ReplyDelete